Construction on the Encore Greenway Park and Gateway, at the corner of North Point Parkway and Encore Parkway, is nearing its listed December 2026 finish. The trail meant to carry Alpha Loop traffic into it won't be ready for a long time after that. The City of Alpharetta approved the contract for that one-mile link this August, and the build is expected to take about 18.5 months. So for its first season or more, Alpharetta's newest trail park will mainly serve people who reach it from the creek side, on the Big Creek Greenway.
What Is Going Up at North Point and Encore
The project is a partnership between the City of Alpharetta and True North 400, the community improvement district for the North Point corridor. True North 400 calls it a gateway feature for the Big Creek Greenway. Its stated job is to give the Alpha Loop a critical connection to the Greenway. Design started in spring 2022, and construction began in February 2025. A groundbreaking followed that March, with Mayor Jim Gilvin and True North 400 board members on hand.
The district's project page lists two dollar figures: a total CID investment of $1,930,000 and a financial commitment of $9,830,000.
The construction log on that page shows how far along the work is:
- Finished: helical piers for the raised boardwalk, a platform for moving wastewater between sewer lines, storm drainage, and site grading.
- Underway: handrails along the raised boardwalk, terraces on the plaza, stone veneer on the retaining walls, and permanent grass where work is wrapping up. Photos of the terraces and a finished retaining wall are dated September 2026.
- Still ahead: beams and decking for the bridges, and the last electrical conduit for future lighting.
No public opening date has been announced yet. December 2026 is the target on the project page, and bridge decking is still on the to-do list. For the next few months, treat the corner as an active construction site, not a finished park.
The Trail Meant to Run Through It Is Still a Contract
On August 17, the Alpharetta City Council approved a $15.99 million design-build contract with Reeves Young. It covers a new Alpha Loop segment running from Encore Parkway to Morrison Lake. Connected Alpharetta reported that this one-mile "Alpha Link" will meet the Big Creek Greenway at Encore Gateway, the park now going up at the corner. The build is expected to take about 18.5 months, and no start date came with the announcement. Even if crews broke ground this fall, that schedule runs into 2028.
Appen Media's Alpharetta-Roswell Herald described the finished trail. It will be 12 feet wide and lit, with its own plaza at Encore Parkway, and it will run through land next to Georgia 400 before ending at Morrison Lake at Haynes Bridge Road. When it's done, Connected Alpharetta says, the trail will link the North Point District with the Lakeview area: the Lakeview mixed-use development, the Georgia 400 Center offices, and the 10-acre Morrison Lake.
Today the Alpha Loop is about six miles long. Its first segment opened in 2020. Alpharetta's part of the Big Creek Greenway runs 12 miles along the creek. The Alpha Link is the piece that ties those two systems together, and it's the last piece to be built.
How the Missing Link Got Cheaper
At first, city officials thought this trail section could cost nearly $25 million. Pete Sewczwicz, Alpharetta's public works director, told Appen Media the city lowered that through phasing and a land swap with the Georgia Department of Transportation. The funding comes from several sources. The city is paying $10 million from transportation sales tax and about $4 million from a 2022 parks bond, and True North 400 is adding almost $1 million.
Councilman John Hipes, who uses the Loop regularly, described that stretch to Appen Media in plain terms:
"When the initial price tag of $25 million was put on the 'Alpha Link,' I thought it would be forever known as the missing link."
Councilmember Katie Reeves told the same outlet, "We're almost to the Greenway, so that is kind of exciting." The gateway is the Greenway end of a phased plan, and it's being finished first. The Loop end, which needs the costlier mile of trail beside Georgia 400, comes later.
What the Gateway Changes for Greenway Users First
Since the Alpha Link is still a long way off, the people who get the most from the new park early on are those already on the Greenway near North Point. The park's design reflects that. True North 400 describes it as a gateway to the Big Creek Greenway, which it calls one of North Fulton's most valuable amenities. The project page says the goal is a stronger connection so the trail can be put to better use by people who live, work, and spend time in the North Point area.
The new pieces are a raised boardwalk with handrails, bridges, plaza terraces, stone-faced retaining walls, and conduit for future lighting. Together they add a finished arrival point on the Greenway at Encore Parkway. Once the Alpha Link opens, the same plaza area becomes the place where Loop traffic from Morrison Lake and Lakeview meets the creek trail. Until then, it's a new stop on the Greenway.
Getting to This Stretch of the Greenway Now
Parking around Encore Parkway takes some planning, and the most obvious spot doesn't work. Ameris Bank Amphitheatre sits at 2200 Encore Parkway, but its visitor guidance says there's no public parking near the venue. Don't count on it as a trailhead.
The established access points nearby are listed on the City of Alpharetta's Greenway map and the Big Creek Greenway parking page:
- North Point entrance, 6698 North Point Parkway. The city map lists restrooms, a bike aid station, and a picnic table here.
- The lot across from North Point Mall, behind Ethan Allen, about 0.2 miles north of Encore Parkway. This is the closest listed parking to the new park.
- Haynes Bridge Road access, about 0.3 miles east of North Point Parkway.
- Rock Mill Park, 3100 Kimball Bridge Road, which the city map lists as a Greenway access point with parking.
The North Point Parkway corridor also has food stops before or after a ride. Vincent Bakery is at 5950 North Point Parkway, Suite 129, and Project LeanNation is at 5966 North Point Parkway, Suite 110. For a quick stop with kids, there's a Chick-fil-A at 6085 North Point Parkway.
Watch for the bridge decking. It's one of the last major items on the gateway's construction list, so once it's in, the park is close to done. The Alpha Link is on a separate schedule. Until Reeves Young starts work along Georgia 400, getting from Morrison Lake to the creek will still mean the roads you use today.